Planning and scheduling of a two-storey cenro lamut office building/ Jealvin P. Bambico, Franz Jerome R. Camarao, Nicolo Mark P. Dychitan, Abigail C. Guingahan, Helen Grace R. Lacar and Rustom C. Pineda

By: Contributor(s): Material type: TextTextPublication details: Bayombong: Nueva Vizcaya State University, 2023.Description: x, 194 leaves : illustrations (some colored), photos ; 28 cm
Item type: Undergraduate Research
Tags from this library: No tags from this library for this title. Log in to add tags.
Star ratings
    Average rating: 0.0 (0 votes)
Holdings
Item type Current library Call number Status Barcode
Undergraduate Research Nueva Vizcaya State University - Bayombong Campus General Reference Section U (BSCE) B199p 2023 (Browse shelf(Opens below)) Not for loan U2031

Construction planning, which involves choosing the appropriate software, defining the various work activities, estimating the time and resources required for each activity, and identifying any interactions between the various work tasks, is a crucial and challenging task in the management and execution of building projects. The purpose of the research is to outline the scheduling and planning for a two-storey CENRO Office Building in Bannit, Payawan Lamut, Ifugao. This study used quantitative research.

The estimated project cost reached about Php 13.5 M which will last for 200 working days (excluding Sundays, and holidays) as computed in the critical path in the PERT/CPM. Thus, the researchers conclude that managing a construction project in an economical way involves careful planning and scheduling.
Keywords: construction planning, cost estimate, scheduling, PERT/CPM

Research paper (Bachelor of Science in Civil Engineering)

Includes bibliographical references and appendices

There are no comments on this title.

to post a comment.

NUEVA VIZCAYA STATE UNIVERSITY

A leading University in education, innovation and sustainable development

@2024 NVSU | Powered by : Koha